Insight

Arbitration Awards: U.S. Fifth Circuit Confirms Judicial Deference

Published on: June 3, 2025

Arbitration is a favored method of dispute resolution in the energy and construction sectors, where complex, high-value contracts often generate multimillion-dollar disputes. Understanding the courts' standard of review of arbitration awards directly impacts risk assessment, contract drafting, and dispute resolution strategies. A recent U.S. Fifth Circuit decision reinforces the limited grounds for judicial intervention, a principle that remains central to the effectiveness of arbitration as an efficient alternative to litigation.

In United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, a drilling subcontractor obtained a $1.7 million arbitration award against the general contractor for standby costs incurred on a pipeline installation project. The subcontractor incurred costs when ordered to stop work for causes outside its control, including delayed permits, mud infiltration, and COVID-19. The subcontract contained a provision that called for reimbursement of standby costs. On appeal, the general contractor sought to vacate the award in the U.S. Northern District of Texas, arguing that the arbitration panel failed to properly interpret various contract provisions related to standby costs and exceeded its authority and acted in manifest disregard of Texas law in interpreting the contract.

The Federal Arbitration Act, 9 USC §10 (“FAA”) applies and provides the exclusive grounds to vacate an award: corruption, fraud, evident partiality, misconduct in refusing to postpone the hearing, refusing to hear evidence, or where arbitrators exceeded their powers. The U. S. Fifth Circuit Court of Appeals noted that the FAA was enacted to create a national policy favoring arbitration; the arbitrator’s authority derives from the parties’ contract; and once parties agree to arbitrate, they “bargain for” the arbitrator’s, not the court’s, interpretation of their contract.

The Court instructed that a party challenging an award bears a high burden to show that the arbitrator ignored the contract. It is not sufficient to show the arbitrator erred in interpreting the contract. The question the court asks is “whether the arbitrators construed the contract at all” not “whether they construed it correctly.” A court should not reassess the merits of the arbitrator’s decision. Here, the award recited the pertinent contract terms and the arbitrators’ analysis. This showed the arbitrators considered the contract provisions, thus ending the Court’s inquiry.

The Court rejected the argument that the arbitrators manifestly disregarded the law in interpreting the contract. “Manifest disregard” – a judicially-created concept – is not a freestanding ground for vacatur. It does not serve as a separate basis to establish that arbitrators exceeded their powers. Otherwise, the FAA’s stated grounds for vacatur would be expanded to essentially a “full-bore” judicial review process.*

However, the Circuits are split on the validity of manifest disregard of the law or contract as a basis to vacate an award. See for example, Dewan v. Walia, where the U.S. Fourth Circuit Court of Appeals vacated an award after finding the arbitrator’s contract interpretation ‘untenable.”

Mary Anne Wolf, PE, FCIArb, is an arbitrator, mediator, and attorney in construction, energy, commercial and complex cases.

References:

United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, 2025 WL 1218096 (5th Cir. 2025).

Dewan v. Walia, 544 Fed Appx 240 (4th Cir. 2013).

* Hall Street Assoc., LLC v. Mattel, 128 S.Ct. 1396 (2008).

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Keogh Cox's Win in Toledo Bend Litigation Could Have National Impact in Flood Hazard Litigation

In a decision released October 9, 2013, the U.S. Fifth Circuit upheld the grant of the defendants' Motion to Dismiss by concluding that the Federal Power Act ("FPA") preempts property damage claims based in Louisiana state tort law where the alleged damage is the result of operations that comply with the FERC-issued license. Simmons v. Sabine River Authority, No. 12-30494, - F.3d - , (5th Cir. 10/09/2013).

This issue, recognized as a question of first impression in the Fifth Circuit, arose in a case where the plaintiffs, all Louisiana owners and residents of property located downstream from the federally-licensed hydroelectric Toledo Bend Dam situated on the Sabine River, sued Sabine River Authority of Louisiana and various Entergy defendants to recover damages for flooding incidents and to enjoin the opening of the Dam's flood gates in such a way as to cause inundation of the downstream properties.

On behalf of defendants, Keogh Cox moved to dismiss the suit by claiming state tort law claims for damages and injunctive relief interferes with the exclusive authority of the Federal Energy Regulatory Commission ["FERC"] to regulate and control the operations of the federally-licensed Toledo Bend project such that the plaintiffs' claims were preempted under the FPA. The District Court granted the motion after extensive briefing and argument by Keogh Cox attorneys, John P. Wolff, III, Nancy B. Gilbert, Martin E. Golden, and Virginia J. McLin.

In affirming the district court's ruling, the Fifth Circuit recognized U.S. Supreme Court precedent that has interpreted the FPA as "occupying the field of public water use and power generation except for water use rights." As a result, in accord with Ninth Circuit law, it interpreted the general savings clause in the FPA [16 U.S.C. § 821] narrowly to exempt only "a state property law regime [that] enables users of streams and wells to obtain proprietary rights in a continuing quantity of water." The Court also recognized that state damage claims can have the same effect as a state regulation and may serve as a collateral attack on a federal license, such that it refused to interpret the limited savings clause [16 U.S.C. § 803(c)] to permit "state tort law to supplant FERC's exclusive control of dam operations." Because "applying state tort law to set the duty of care for the operation of the FERC-licensed project would 'stand as an obstacle to the accomplishment and execution of the full purposes and objectives' of the FPA," the Fifth Circuit held plaintiffs' state law property damages claims were conflict preempted under the FPA.

That a single federal agency should control public water use and dam operations was noted to be especially appropriate because the Toledo Bend Dam spans Texas and Louisiana state lines and, if not preempted, different causes of action and standards of conduct could have been imposed under the laws of the two states.

Insight

Who’s Left Holding the Bag? Indemnity in Construction Contracts

The period of time before the contract is signed in one of optimism. After all, few sign a contract expecting problems. But if you do not consider the many "what ifs," you may be left holding the bag. And this "bag" may include indemnity provisions which could force you respond for the actions of other parties.

Many contracts include "indemnity" or "hold harmless" provisions. Black's Law Dictionary defines indemnity as "a duty to make good any loss, damage, or liability incurred by another." Like many states, Louisiana allows one party to agree to pay for the damages caused by the fault of the other, if this intention is sufficiently expressed. However, there are broad statutory exceptions that can nullify the indemnity requirement.

Parties to construction contracts should be careful not to blindly rely upon indemnity provisions because the Louisiana legislature in La. R.S. 9:2780.1 declared invalid any indemnity provision where a party seeks indemnity from another for its own fault.

Despite the broad nullification of certain types of indemnity provisions in construction contracts, current Louisiana law allows a party to be indemnified for its own fault when the other party obtains insurance to cover the risk, and recovered the cost of insurance in the contract price. For example, a general contractor can require a subcontractor to indemnify the general contractor for the general contractor’s fault, as long as the subcontractor obtains insurance for this obligation, and was paid that amount under the contract.

Indemnity obligations are not always as they seem. Even in the pre-contract period of optimism, you may want to contact an attorney so you won't be left holding the bag.

Chelsea Payne is an associate at Keogh Cox and has been practicing for three years. Her practice mainly relates to construction law and complex litigation. Chelsea enjoys playing tennis and spending time with her family.

Insight

Arbitration Awards: U.S. Fifth Circuit Confirms Judicial Deference

Arbitration is a favored method of dispute resolution in the energy and construction sectors, where complex, high-value contracts often generate multimillion-dollar disputes. Understanding the courts' standard of review of arbitration awards directly impacts risk assessment, contract drafting, and dispute resolution strategies. A recent U.S. Fifth Circuit decision reinforces the limited grounds for judicial intervention, a principle that remains central to the effectiveness of arbitration as an efficient alternative to litigation.

In United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, a drilling subcontractor obtained a $1.7 million arbitration award against the general contractor for standby costs incurred on a pipeline installation project. The subcontractor incurred costs when ordered to stop work for causes outside its control, including delayed permits, mud infiltration, and COVID-19. The subcontract contained a provision that called for reimbursement of standby costs. On appeal, the general contractor sought to vacate the award in the U.S. Northern District of Texas, arguing that the arbitration panel failed to properly interpret various contract provisions related to standby costs and exceeded its authority and acted in manifest disregard of Texas law in interpreting the contract.

The Federal Arbitration Act, 9 USC §10 (“FAA”) applies and provides the exclusive grounds to vacate an award: corruption, fraud, evident partiality, misconduct in refusing to postpone the hearing, refusing to hear evidence, or where arbitrators exceeded their powers. The U. S. Fifth Circuit Court of Appeals noted that the FAA was enacted to create a national policy favoring arbitration; the arbitrator’s authority derives from the parties’ contract; and once parties agree to arbitrate, they “bargain for” the arbitrator’s, not the court’s, interpretation of their contract.

The Court instructed that a party challenging an award bears a high burden to show that the arbitrator ignored the contract. It is not sufficient to show the arbitrator erred in interpreting the contract. The question the court asks is “whether the arbitrators construed the contract at all” not “whether they construed it correctly.” A court should not reassess the merits of the arbitrator’s decision. Here, the award recited the pertinent contract terms and the arbitrators’ analysis. This showed the arbitrators considered the contract provisions, thus ending the Court’s inquiry.

The Court rejected the argument that the arbitrators manifestly disregarded the law in interpreting the contract. “Manifest disregard” – a judicially-created concept – is not a freestanding ground for vacatur. It does not serve as a separate basis to establish that arbitrators exceeded their powers. Otherwise, the FAA’s stated grounds for vacatur would be expanded to essentially a “full-bore” judicial review process.*

However, the Circuits are split on the validity of manifest disregard of the law or contract as a basis to vacate an award. See for example, Dewan v. Walia, where the U.S. Fourth Circuit Court of Appeals vacated an award after finding the arbitrator’s contract interpretation ‘untenable.”

Mary Anne Wolf, PE, FCIArb, is an arbitrator, mediator, and attorney in construction, energy, commercial and complex cases.

References:

United States Trinity Services, LLC v. Southeast Directional Drilling, LLC, 2025 WL 1218096 (5th Cir. 2025).

Dewan v. Walia, 544 Fed Appx 240 (4th Cir. 2013).

* Hall Street Assoc., LLC v. Mattel, 128 S.Ct. 1396 (2008).

Mary Anne Wolf, PE, FCIArb

Partner
Arbitration
Award
Construction
Energy
Exceed Powers
Federal Arbitration Act
Manifest Disregard
US Fifth Circuit
Vacate
Vacatur