Insight

Pass-Through Claims and Prescription

Published on: August 3, 2026

In Couvillion Group, LLC v. Plaquemine Parish Government, the Louisiana Court of Appeals for the Fourth Circuit addressed whether the general contractor could recover “pass-through claims” against the owner where those claims would be time-barred if brought directly by the subcontractors. “Pass-through claims” have been described as damage claims that subcontractors “pass through” to the contractor to prosecute an action against the project owner to recover those damages.

In Couvillion, the contractor sued the Parish for delay damages. The trial court awarded $2,782,724 in delay damages, $300,000 of which was for delays incurred by two of the subcontractors.

On appeal, the Parish argued that the contractor could not recover the pass-through claims because any claims for delay that the subcontractors had against the contractor were prescribed (time-barred). The subcontractors sent demand letters after substantial completion in 2013 but did not file suit against the contractor. Under Louisiana law, contract claims are subject to a 10-year prescriptive period. The Parish asserted that by the time trial occurred in 2024, the subcontractor claims had prescribed.

The Fourth Circuit recognized that subcontractors often pass their claims through the contractor to prosecute against the owner to recover those damages. The contractor included those claims in the lawsuit filed against the owner in 2015. When several parties share a cause of action, suit by one party interrupts prescription as to all parties. As such, the court held that prescription was interrupted, and the contractor could recover the pass-through claims against the owner.

This case highlights the importance of identifying and properly preserving pass-through claims early in litigation.

References:

Couvillion Grp., LLC v. Plaquemines Par. Gov't, 2025-0356 (La. App. 4 Cir. 1/7/26), 430 So. 3d 1175, writ denied, 2026-00217 (La. 5/12/26), 430 So. 3d 1090.

‍

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

What is a Design Professional’s Tort Duty?

A design professional’s duties and responsibilities on a construction project generally are outlined in its contract with the owner. Does a design professional’s duty extend to third parties? The Supreme Court recently addressed this issue and held that the design professional’s duty to third parties is limited to the terms of the contract documents.

In Bonilla, a construction worker was injured while performing demolition work on a construction project. The worker, who was a subcontractor on the project, filed suit against the architect and the engineer on the project alleging that these design professionals failed to monitor and supervise the execution of the plans to ensure safety on the job site.

The engineer and the architect filed summary judgment motions arguing that they owed no duty to oversee, supervise, or maintain the construction site. The trial court granted their motions. However, the appellate court found the contract between the architect and the owner may have inferred a duty was owed to the worker.

The appellate court referenced contract provisions that required the architect to make weekly site visits and to report to the owner any deviations from the plans. The court noted that the architect was on site the day of the accident and photographed potential unsafe conditions, which would have deviated from the plans. The appeal court reversed the trial court’s ruling granting summary judgment.

The architect filed a writ with the Louisiana Supreme Court, which reversed the appellate court’s ruling and reinstated summary judgment in favor of the design professionals. The Supreme Court emphasized “the duty owed to an employee of a contractor by an engineer or architect is determined by the express provisions of the contract between the parties.”

While the contract documents required the architect to make weekly visits to the jobsite, the purpose of this duty was to ensure that the owner received the building it paid for and that the progress and quality of the work met the plans. More importantly, the contract also provided that these site visits did not create a duty to supervise construction. In contrast, under the terms of the contract, the contractor had control over construction means and methods and responsibility for site safety, specifically including site safety for all employees.

The clear and unambiguous language of the contract dictated that the design professions owed the worker no duty. Therefore, the Supreme Court held that the architect could not be held liable for failing to perform a duty that it had no responsibility to undertake.

Reference:

Bonilla v. Verges Rome Architects, 2023-00928 (La. 3/22/24), 382 So. 3d 62.

Insight

Construction Law: The Limits of Anti-Indemnity in Louisiana

Louisiana’s anti-indemnity statute applicable to construction contracts, R.S. 9:2780.1, became law in 2011. The statute renders unenforceable any provision in, or collateral to, a construction contract that purports to indemnify or hold harmless a person from liability for its own negligence, or has the effect of doing so. Since the law's passage, few court decisions have interpreted its seemingly broad language and many questions remain as to the law's full impact.

The obvious intent of the anti-indemnity law is to avoid shifting liability away from a party at fault to another person. To this end, the language in the statute nullifies any agreement that has "the effect of holding the person at fault harmless.” But what about "limit of liability" provisions? Arguably, such provisions have the effect of holding harmless the party at fault. Does a limit of liability provision, otherwise valid and enforceable under Louisiana law, run afoul of the anti-indemnity statute? After all, those parties with superior bargaining power in construction contracts will seek to insulate themselves from liability to the fullest extent allowed by law, and will look for alternatives to the indemnity provisions that now expressly violate public policy.

One court recently held that R.S. 9:2780.1 does not prohibit a limit of liability provision in a construction contract. In Patriot Contracting, LLC v. Star Insurance Company, (E.D. La. 3/01/2018), the construction contract contained a provision that excluded liability of the architect for good faith decisions made during contract administration. The plaintiff/contractor alleged that the architect was negligent in its contract administration duties and caused it to suffer economic loss. The court dismissed the claim, rejecting the contractor’s argument that the provision violated the anti-indemnity law.

The Patriot court explained that the statute prohibits an indemnity agreement, i.e., where one party agrees to reimburse a second party for damages for which the second party becomes liable to a third party. However, the anti-indemnity law did not impact the provision that excluded the contractor’s right to recover from the architect. Thus, at at least according to one court, parties in construction contracts are still free to include limit of liability provisions.

Mary Anne Wolf is an engineer/attorney with a construction background who represents design professionals, contractors, and others in construction litigation. She also gives seminars on the subject. She enjoys travel, yoga, and encouraging her husband in his gardening and cooking endeavors.

News

Mary Anne Wolf will present Construction Insurance at the LSU and LSBA Construction Law CLE Program.

Mary Anne Wolf will present Construction Insurance at the LSU and LSBA Construction Law CLE Program on September 20, 2024.

Chelsea A. Payne

Partner
Prescription
Construction
Contractors