Insight

Supreme Court Rules Against Broad Application of Indemnity Provision in Engineer’s Contract

Published on: June 3, 2020

The Supreme Court ruling in Couvillion Group, LLC v. Plaquemines Parish Government, 2020 -00074 (La. 4/27/20) is a reminder that an indemnity claim must be sufficiently related to the principal demand and that contract indemnity provisions are to be strictly construed.

In Couvillion, the general contractor sued the owner of a public works port project for contract delay damages resulting from a cease work order issued to allow redesign of a fuel tank platform. When the contractor submitted its delay claim, the owner requested that its project engineer review it and make recommendations. The engineer recommended payment of a little over $1 million dollars. When the owner refused to pay, the contractor sued. In response, the owner filed a third-party demand against the engineer alleging that its recommendation was erroneous and excessive and that, if it was bound by the engineer’s recommendation, then the engineer must indemnify the owner.

On behalf of the engineer, Keogh Cox attorneys argued that the engineer should not be required to reimburse the owner for any delay costs and asked for dismissal through an exception of no cause of action. Code of Procedure Article 1111 provides that a defendant in a principal action may bring in any person who may be liable to him for all or part of the principal demand. Here, that was not the situation. The engineer was not liable to the owner for any part of the contractor’s delay claim because the engineer did not cause the delay. The delay damages were incurred before the engineer made a recommendation for payment. The events giving rise to the two claims were separate and distinct: the main demand arose from the project delay and the third- party demand arose from the engineer’s recommendation of the claim amount. The Court commented that the principal claim against the owner for delay damages was too attenuated from the owner’s claim against the engineer, thus the third-party demand was improper.

The owner also relied on the indemnity provision in the engineer’s contract that required the engineer to indemnify the owner against any and all claims for personal injury or “damages to property” that may arise from its services. The Court held that the plain meaning of the term did not include the economic-only losses related to the subject delay claim. The Court further reasoned that indemnity agreements are to be strictly construed, rejecting the owner’s broader interpretation.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

Case on a Wire - Last Minute Fax Filing

The Louisiana Supreme Court recently held that a request for service of process made by facsimile filing within ninety days from the filing of the petition, but not perfected until after the ninety days has passed, is a timely request for service of process under LSA-C.C.P. art. 1201. See Brenda Morales and Jerson Rodriguez v. State of Louisiana Through the Board of Supervisors of LSU Through Earl K. Long Medical Center, 12-2301 (La. 1/11/13), --So.3d---.

In reaching its decision, the Morales court addressed whether Louisiana's Facsimile Filing Statute, LSA- R.S. 13:850, required both the payment of fees and the receipt of the original request for service before service is considered to have been requested. Under Louisiana procedure, the petitioner has 90 days to request service upon all defendants. See LSA-C.C.P. art. 1201. When service is not timely requested, the case can be involuntarily dismissed without prejudice on the motion of another party. See LSA-C.C.P. art. 1672(C). This dismissal can result in a later bar to the claim if the re-filed suit is then prescribed and the defendants can show bad faith in the failure to request service or the suit involves a claim against the state or a political subdivision of the state.

In Morales, the Louisiana First Circuit had found that the request for service was not timely because the fax filing fees were not paid by the attorney until after the ninetieth day. The First Circuit relied on the Louisiana Supreme Court's previous ruling in Trachant v. State of Louisiana, Louisiana State University Health Sciences Center, 08-0978 (La. 1/21/09), 5 So.3d 832 which stated that "[a] valid request for service under La. R.S. 13:6107(D)(1) is made when the clerk receives the request for service and can then act on it." The First Circuit reasoned that a clerk cannot act upon a request for service when there is no original request and the corresponding fees had not been paid. However, Trachant did not involve fax filing and instead considered whether a request for service is effective when it is placed in the mailbox or when it is received by the clerk. This is sometimes referred to as the "mailbox rule." The Trachant court held that actual receipt of the request was required.

The Louisiana Supreme Court in Morales disagreed with the First Circuit and found that the clerk can "act upon" receipt of the facsimile filing. The Court emphasized that LSA- R.S. 13:850(A) provides that a facsimile filing "shall be deemed complete at the time that the facsimile transmission is received and a receipt of transmission has been transmitted to the sender by the clerk of court." The Morales Court harmonized its ruling with Trachant by finding that the Court has always held that the receipt of the request must occur within the 90 day period.

Even after Morales, a request for service of process should be followed by the prompt mailing of the original signed document and the required transmission fee. However, Morales indicates that Louisiana's highest court is likely to give consideration to preserving a claim when interpreting the otherwise strict requirements of Louisiana's Facsimile Filing Statute.

Insight

Fourth Circuit Brings Clarity to Peremption Statute in Suit Against Design Professional

The question addressed in MR Pittman Group, LLC versus Plaquemines Parish Government, 2015-0396 (La.App. 4 Cir. 12/2/15) was whether the five-year peremptive period set by La. R.S. 9:5607 displaces Louisiana’s general one-year prescriptive period set by La. C.C. art. 3492, when applied to tort claims against design professionals. Finding a contractor’s claim against the project engineers prescribed, the MR Pittman court held that the one-year prescriptive period governs tort claims against design professionals.

La. R.S. 9:5607 explicitly provides a peremptive period that extinguishes all claims against architects, engineers and other design professionals five years after the project is completed, thus limiting design professional liability associated with the project. The MR Pittman plaintiff/contractor argued that the statute also eliminates the one-year prescriptive period and instead creates a special five-year prescriptive period, which allowed the contractor up to five years to bring its claim against the engineers to recover for delay and other extra costs allegedly resulting from deficiencies in the construction plans. This interpretation effectively expands tort liability by increasing the time period for bringing a tort claim from one to five years. In rejecting this argument, the MR Pittman court clarified that under the statute any claimant has no more than five years after project completion to bring suit against the design professional for any cause. However, a tort claimant still has only one year to file suit from the date he “knew or should have known” of damage caused by the alleged wrongful actions of the design professional.

A secondary question addressed in MR Pittman was the date of commencement of the one-year prescriptive period, which under La. C.C. 3492 commences to run from the day damage is sustained. The defendant/engineers argued that prescription commenced when the contractor first became aware of the alleged design deficiencies early in construction, as evidenced by the contractor’s notice to the owner of the deficiencies. The contractor argued that it could not fully appreciate its damages until the change orders were resolved later in the project. Citing Louisiana Supreme Court precedent holding that the quantum of damages need not be certain or fully incurred to trigger commencement of prescription, Harvey v. Dixie Graphics, Inc., 593 So.2d 351, 354 (La. 1992), the court agreed with the engineers’ position and dismissed the claims.

Insight

Good Restrictions Can Make Good Neighbors

Picture it – you purchase a new home in a quiet, family-friendly neighborhood. On your first night, you notice that the neighbors are having a party – a big loud party. Your haven of peace and tranquility is interrupted by thumping bass and the shrieks of people jumping into a pool. The next day, the neighbors are gone, and the block is quiet again. However, the party returns the next weekend, bigger and louder than before. You do some research and find the house is listed on a popular website for short term rentals. What do you do?

This is the exact question that was posed to the Louisiana Court of Appeals for the Second Circuit in Marina Homeowners Association, Inc. v. Cahill. In that case, the Marina Homeowner’s Association filed a petition seeking declaratory judgment against the owner of the house on the basis that the use of the home as a short-term rental violated the covenants of the homeowner’s association. In response, the property owners argued that the covenants had expired and were no longer applicable. Therefore, they claimed they were free to use their property as they saw fit.

Many homeowners in Louisiana are familiar with building restrictions. Authority for the issuance of building restrictions is found in Louisiana Civil Code article 775. A building restriction is a real right under Louisiana Civil Code article 777. However, Louisiana Civil Code article 778 provides that if there is doubt as to the existence, validity, or extent of building restrictions, the issue should be resolved in favor of the unrestricted use of the immovable. These articles also provide a subsequent purchaser of the immovable property is also bound by the building restrictions if they are recorded in the public records.

The building restrictions for the subdivision at issue provided that the restrictions had a term of twenty years and then would renew automatically in ten-year periods. These restrictions bound the original property owners and all subsequent property owners. The court found that even though the original twenty-year term for the building restrictions had expired, the restrictions would automatically renew unless amended by the Association. Therefore, the property owner’s house was subject to the building restrictions.

Importantly for this case, the building restrictions specifically prohibited the use of the property for any reasons other than residential purposes. Therefore, the operation of a short-term rental was a violation of the building restrictions.

The Homeowners Association prevailed in this case – the property owners were no longer able to use their property for short term rentals. As the moral of the story – to be a good neighbor – it helps to follow the rules. And it is always important to check the fine print to know what those rules are!

References:

Marina Homeowners Ass'n, Inc. v. Cahill, 56,423 (La. App. 2 Cir. 8/27/25), 420 So. 3d 782.

Mary Anne Wolf, PE, FCIArb

Partner
Contracts
Engineers
Supreme Court