Supreme Court Rules Against Broad Application of Indemnity Provision in Engineer’s Contract

Published on: June 3, 2020

The Supreme Court ruling in Couvillion Group, LLC v. Plaquemines Parish Government, 2020 -00074 (La. 4/27/20) is a reminder that an indemnity claim must be sufficiently related to the principal demand and that contract indemnity provisions are to be strictly construed.

In Couvillion, the general contractor sued the owner of a public works port project for contract delay damages resulting from a cease work order issued to allow redesign of a fuel tank platform. When the contractor submitted its delay claim, the owner requested that its project engineer review it and make recommendations. The engineer recommended payment of a little over $1 million dollars. When the owner refused to pay, the contractor sued. In response, the owner filed a third-party demand against the engineer alleging that its recommendation was erroneous and excessive and that, if it was bound by the engineer’s recommendation, then the engineer must indemnify the owner.

On behalf of the engineer, Keogh Cox attorneys argued that the engineer should not be required to reimburse the owner for any delay costs and asked for dismissal through an exception of no cause of action. Code of Procedure Article 1111 provides that a defendant in a principal action may bring in any person who may be liable to him for all or part of the principal demand. Here, that was not the situation. The engineer was not liable to the owner for any part of the contractor’s delay claim because the engineer did not cause the delay. The delay damages were incurred before the engineer made a recommendation for payment. The events giving rise to the two claims were separate and distinct: the main demand arose from the project delay and the third- party demand arose from the engineer’s recommendation of the claim amount. The Court commented that the principal claim against the owner for delay damages was too attenuated from the owner’s claim against the engineer, thus the third-party demand was improper.

The owner also relied on the indemnity provision in the engineer’s contract that required the engineer to indemnify the owner against any and all claims for personal injury or “damages to property” that may arise from its services. The Court held that the plain meaning of the term did not include the economic-only losses related to the subject delay claim. The Court further reasoned that indemnity agreements are to be strictly construed, rejecting the owner’s broader interpretation.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

When No Higher Court Remains

On April 20, 2010, BP's Deepwater Horizon rig exploded at a cost of eleven lives. What followed was the largest accidental marine oil spill in history. In the aftermath, BP looked for a solution, ostensibly to cap its exposure and address a swirling PR disaster. BP began to actively negotiate a settlement.

On March 2, 2012, BP agreed to a detailed settlement which set forth specific criteria for recovery under the Fund created by the Agreement. In August of that year, BP asked U.S. District Judge Carl Barbier to approve the settlement. The Agreement was approved.

Despite championing the settlement, BP later filed a lawsuit seeking to set aside the settlement, unless it was interpreted as suggested by BP. BP's challenges were rejected by the Federal District Court. Thereafter, the New Orleans-based Fifth Circuit Court of Appeals affirmed that ruling in a 2-to-1 decision. BP then applied for a Petition of Writ for Certiorari with the United States Supreme Court in a final challenge to the settlement.

About BP's legal maneuvers, Samuel Issacharoff, a New York University Law Professor, said the following: "This case is about a contract that BP signed that it now wishes it hadn't."

One of BP's primary complaints was that, in effect, the settlement could be interpreted to provide recovery for individuals or businesses who could not show a direct link between a financial downturn and the spill. In response, it was stated that the settlement was crafted to use objective measures to gauge whether losses are recoverable.

On December 8, 2014, the U.S. Supreme Court rejected BP's Petition for Writ of Certiorari. As such, the settlement agreement first proposed by BP will remain in place. No higher court remains.

Under the Agreement, potential claimants have 6 months from the Supreme Court's Petition denial to file claims.

Insight

What is a Design Professional’s Tort Duty?

A design professional’s duties and responsibilities on a construction project generally are outlined in its contract with the owner. Does a design professional’s duty extend to third parties? The Supreme Court recently addressed this issue and held that the design professional’s duty to third parties is limited to the terms of the contract documents.

In Bonilla, a construction worker was injured while performing demolition work on a construction project. The worker, who was a subcontractor on the project, filed suit against the architect and the engineer on the project alleging that these design professionals failed to monitor and supervise the execution of the plans to ensure safety on the job site.

The engineer and the architect filed summary judgment motions arguing that they owed no duty to oversee, supervise, or maintain the construction site. The trial court granted their motions. However, the appellate court found the contract between the architect and the owner may have inferred a duty was owed to the worker.

The appellate court referenced contract provisions that required the architect to make weekly site visits and to report to the owner any deviations from the plans. The court noted that the architect was on site the day of the accident and photographed potential unsafe conditions, which would have deviated from the plans. The appeal court reversed the trial court’s ruling granting summary judgment.

The architect filed a writ with the Louisiana Supreme Court, which reversed the appellate court’s ruling and reinstated summary judgment in favor of the design professionals. The Supreme Court emphasized “the duty owed to an employee of a contractor by an engineer or architect is determined by the express provisions of the contract between the parties.”

While the contract documents required the architect to make weekly visits to the jobsite, the purpose of this duty was to ensure that the owner received the building it paid for and that the progress and quality of the work met the plans. More importantly, the contract also provided that these site visits did not create a duty to supervise construction. In contrast, under the terms of the contract, the contractor had control over construction means and methods and responsibility for site safety, specifically including site safety for all employees.

The clear and unambiguous language of the contract dictated that the design professions owed the worker no duty. Therefore, the Supreme Court held that the architect could not be held liable for failing to perform a duty that it had no responsibility to undertake.

Reference:

Bonilla v. Verges Rome Architects, 2023-00928 (La. 3/22/24), 382 So. 3d 62.

Insight

To Err is Human, To Rescind-Declined

The Louisiana Supreme Court recently addressed the impact of contractual "errors" in Cynthia Fry Perionnet and Elizabeth Fry Franklin v. Matador Resources Company, 2012-2292, 2012-2377, -- So. 3d --.

The Perionnet case involved a dispute over the intent of a contract to extend a mineral lease. The property owners believed that the lease was extended as to only 168.95 acres of nonproducing land. The defendant/lessors argued that the contract contemplated that the lease would extend to the entire 1850.34 acres to include producing wells. Plaintiffs/property owners argued that their unilateral error regarding the terms of the contract was ground for rescission. The jury ruled in favor of the defendant/lessors. The Court of Appeal reversed. The Supreme Court granted writs.

The Perionnet Court began its opinion with an overview of basic tenets of contract law. The Louisiana Civil Code defines a contract as "an agreement by two or more parties whereby obligations are created, modified, or extinguished." La. C.C. art. 1906. Contracts are formed through offer and acceptance. La. C.C. art. 1927. Once formed, contracts have "the effect of law for the parties and may be dissolved only through the consent of the parties or on grounds provided by law." La. C.C. art. 1983. One such "ground" under Louisiana law is "error." La. C.C. art. 1948.

The Louisiana Civil Code recognizes two forms of error: mutual error (both parties are mistaken) or unilateral error (only one party is mistaken). However, for either error to cause the dissolution of a contract, the error (1) must effect the cause of the obligation and (2) the other party must have known that the matter impacted by the error was the reason for the contract. La. C.C. art. 1949. In a case of mutual error, the court can reform the contract. Either partial or full rescission is the only remedy available for unilateral error. La. CC. art. 1952.

A party challenging a contract for unilateral error must also prove that the error was excusable. "Louisiana jurisprudence is sprinkled with cases which deny relief to the parties who claim an agreement should be invalidated because of unilateral error which is caused, in large part, by the complaining party's inexcusable ignorance, neglect or want of care." Id. p. 25.

The Perionnet Court found that the plaintiffs' alleged mistake was inexcusable. The defendants demonstrated that: 1) plaintiffs could show no excuse for failing to read and understand the contract; 2) plaintiffs' agents who negotiated and reviewed the contract were self-proclaimed experts in oil and gas; and 3) the original lease was on the plaintiffs' agent's own forms. The Court found a "sea of flags" in the written agreement that should have notified the experienced plaintiffs that the agreement extended to the entire property. Therefore, the Court found that the mistake was easily detectable and could have been rectified by a minimal amount of care, i.e. "by simply reading the document and/or requesting simple changes to the written offer before acceptance." Id. at 30.

The Supreme Court's Perionnet decision serves as a healthy reminder of a basic concept - read your contracts. Although to err may be human, it can affect your bottom line.