Insight

Supreme Court Rules Against Broad Application of Indemnity Provision in Engineer’s Contract

Published on: June 3, 2020

The Supreme Court ruling in Couvillion Group, LLC v. Plaquemines Parish Government, 2020 -00074 (La. 4/27/20) is a reminder that an indemnity claim must be sufficiently related to the principal demand and that contract indemnity provisions are to be strictly construed.

In Couvillion, the general contractor sued the owner of a public works port project for contract delay damages resulting from a cease work order issued to allow redesign of a fuel tank platform. When the contractor submitted its delay claim, the owner requested that its project engineer review it and make recommendations. The engineer recommended payment of a little over $1 million dollars. When the owner refused to pay, the contractor sued. In response, the owner filed a third-party demand against the engineer alleging that its recommendation was erroneous and excessive and that, if it was bound by the engineer’s recommendation, then the engineer must indemnify the owner.

On behalf of the engineer, Keogh Cox attorneys argued that the engineer should not be required to reimburse the owner for any delay costs and asked for dismissal through an exception of no cause of action. Code of Procedure Article 1111 provides that a defendant in a principal action may bring in any person who may be liable to him for all or part of the principal demand. Here, that was not the situation. The engineer was not liable to the owner for any part of the contractor’s delay claim because the engineer did not cause the delay. The delay damages were incurred before the engineer made a recommendation for payment. The events giving rise to the two claims were separate and distinct: the main demand arose from the project delay and the third- party demand arose from the engineer’s recommendation of the claim amount. The Court commented that the principal claim against the owner for delay damages was too attenuated from the owner’s claim against the engineer, thus the third-party demand was improper.

The owner also relied on the indemnity provision in the engineer’s contract that required the engineer to indemnify the owner against any and all claims for personal injury or “damages to property” that may arise from its services. The Court held that the plain meaning of the term did not include the economic-only losses related to the subject delay claim. The Court further reasoned that indemnity agreements are to be strictly construed, rejecting the owner’s broader interpretation.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

La. Supreme Court Determines Impact of Failure to Pay Filing Fee in Medical Review Panel

The Louisiana Supreme Court recently held that failure to pay filing fees necessary to add a defendant does not invalidate the proceeding as to other defendants. Prior to the ruling, Louisiana courts held that a failure to pay for one defendant invalidated the entire proceeding.

In Kirt v. Metzinger 2019-C-1162 (La. 04/03/20), plaintiffs requested a medical review panel after the death of their mother due to complications after surgery. Plaintiffs named three defendants—two doctors and the hospital. A letter from the Patient’s Compensation Fund Oversight Board (PCF) was mailed to the plaintiffs, confirming that the defendants were qualified under the Louisiana Medical Malpractice Act, and informing the plaintiffs that they were required by La. R.S. 40:1231.8 to pay a filing fee of $100 per named defendant within forty-five days of the mailing of the letter. Plaintiffs responded, requesting to add two additional defendants to the panel, one of whom was an unidentifiable nurse. Plaintiffs also included payment of $500.

The PCF responded that it was unable to add the nurse without proper identification. Three weeks later, plaintiffs notified the PCF they were also unable to identify the nurse. Upon request, Parish Anesthesia was added to the panel instead. Nearly five months later, plaintiffs provided the PCF with the identity of the nurse in question and requested she be added. The PCF sent confirmed the addition and requested another $100 filing fee which was never paid. Nevertheless, the medical review panel thereafter determined that none of the defendants, including the nurse, breached their standard of care. Suit followed against all defendants.

The defendants moved for summary judgment, arguing that the failure to pay the additional filing fee invalidated the proceeding as to all defendants. The trial court granted this motion, and the appellate court affirmed. Reversing the lower courts, the Supreme Court found that the failure to pay the additional $100 filing fee did not invalidate the entire proceeding. The court observed that separate confirmation letters sent by the PCF provided a different forty-five day period during which to pay the filing fee tied to each individual defendant.

The Kirt court stated: “[t]he notion of ‘one filing fee’ for every panel proceeding cannot be reconciled with the different payment deadlines that arise when the PCF sends separate letters confirming defendants’ qualified status. A single filing fee cannot be subject to different payment deadlines.” The court dismissed only the nurse and remanded the remainder of case to the lower courts.

Chad A. Sullivan is a partner with Keogh, Cox & Wilson, Ltd. Prior to becoming an attorney, he worked as a licensed Registered Nurse. He utilizes his background in nursing on a daily basis in his law practice that primarily focuses on automobile liability, medical malpractice, nursing home litigation, healthcare professional licensure and discipline, and products liability.

Insight

When No Higher Court Remains

On April 20, 2010, BP's Deepwater Horizon rig exploded at a cost of eleven lives. What followed was the largest accidental marine oil spill in history. In the aftermath, BP looked for a solution, ostensibly to cap its exposure and address a swirling PR disaster. BP began to actively negotiate a settlement.

On March 2, 2012, BP agreed to a detailed settlement which set forth specific criteria for recovery under the Fund created by the Agreement. In August of that year, BP asked U.S. District Judge Carl Barbier to approve the settlement. The Agreement was approved.

Despite championing the settlement, BP later filed a lawsuit seeking to set aside the settlement, unless it was interpreted as suggested by BP. BP's challenges were rejected by the Federal District Court. Thereafter, the New Orleans-based Fifth Circuit Court of Appeals affirmed that ruling in a 2-to-1 decision. BP then applied for a Petition of Writ for Certiorari with the United States Supreme Court in a final challenge to the settlement.

About BP's legal maneuvers, Samuel Issacharoff, a New York University Law Professor, said the following: "This case is about a contract that BP signed that it now wishes it hadn't."

One of BP's primary complaints was that, in effect, the settlement could be interpreted to provide recovery for individuals or businesses who could not show a direct link between a financial downturn and the spill. In response, it was stated that the settlement was crafted to use objective measures to gauge whether losses are recoverable.

On December 8, 2014, the U.S. Supreme Court rejected BP's Petition for Writ of Certiorari. As such, the settlement agreement first proposed by BP will remain in place. No higher court remains.

Under the Agreement, potential claimants have 6 months from the Supreme Court's Petition denial to file claims.

Insight

Less Than Obvious State of “Open and Obvious” Defense

The “open and obvious” defense remains alive and well in Louisiana according to an article penned recently by Professor John M. Church of the LSU Law Center for the Louisiana Association of Defense Counsel. In April 2013, the Louisiana Supreme Court announced Broussard v. State of Louisiana, 2012-1238 (La. 4/5/13), 113 So.3d 175, which muddied the waters regarding use of the “open and obvious” defense. Some read Broussard as a pronouncement that the “open and obvious” defense was essentially dead in Louisiana. However, as reflected in Professor Church’s article, subsequent Louisiana Supreme Court decisions have given new life to the defense.

The defense is based upon the premise that an “open and obvious” defect is non-hazardous, because a reasonably-attentive plaintiff could or should have avoided the harm in the exercise of due care. Before Broussard, courts routinely ruled that a defendant owed no duty to a plaintiff when the alleged defect was “open and obvious.” Following Broussard, courts began to shift the analysis from a question of duty (an issue of law) to a factor that should be considered when analyzing a potential breach of that duty (an issue of fact). As such, some courts concluded that the defense was not properly addressed at the summary judgment stage.

In October 2014, the Supreme Court appeared to alter course when it affirmed a summary judgment granted on grounds that the alleged defect presented an open and obvious condition. See Bufkin v. Felipe’s Louisiana, LLC, 2014-0288 (La. 10/15/14), — So.3d — 2014 WL 5394087. In reaching this decision, the Bufkin Court focused on the duty element of plaintiff’s case, which seemingly contradicted prior interpretations of Broussard. Thereafter, the Court went even further, affirmatively stating that “[a]ny reading of Broussard interpreting it as a limit on summary judgment practice involving issues of unreasonable risk of harm is a misinterpretation of the Broussard case.” Allen v. Lockwood, 2014-1724 (La. 2/13/15), 156 So.3d 650.

According to Professor Church, Bufkin and Allen reflect a shift back to an analysis of the open and obvious defense on the duty level and remove any doubt regarding whether summary judgment is appropriate in this setting. Professor Church anticipates that the Supreme Court will continue to clarify this doctrine in future decisions. For now, Broussard remains an obstacle, albeit shrinking, in the defense of trip and fall claims.

Author: C. Reynolds LeBlanc

Mary Anne Wolf, PE, FCIArb

Partner
Contracts
Engineers
Supreme Court