Will Your Arbitration Clause Be Upheld?

Published on: September 3, 2026

Many in the construction industry favor arbitration and often include an arbitration clause in their contracts. Although best practice dictates that both parties sign the contract to eliminate doubt as to legal enforceability, in practice, one or both parties sometimes fail to sign. Instead, the parties show their mutual “meeting of the minds” that an agreement has been reached by performing and accepting the work. However, if a dispute arises, will an arbitration provision in an unsigned contract be enforced?

In Patriot Construction & Industrial, LLC v. Buquet& LeBlanc, Inc., when a dispute arose over the subcontractor’s work, the general contractor sought to invoke the arbitration clause in its standard subcontract. The subcontractor argued that the unsigned, red-lined subcontract its estimator had returned to the general contractor was not enforceable, and thus neither was the arbitration clause. The court found agreement on price and scope but found that no agreement was reached on the other terms because the estimator did not have authority to bind the subcontractor. Further, a provision in the contract required that changes be initialed by both parties, yet the subcontractor’s authorized agent had not initialed any of the changes.

The Court held that the arbitration clause was not binding. The Court emphasized that Louisiana law favors arbitration; however, it held “arbitration is a matter of contract, and a party cannot be required to submit to arbitration any dispute to which he has not so agreed.” The question of who is bound by an arbitration agreement is determined from the intent of the parties as expressed in the terms of the contract. If the contract is deemed void because it was not properly confected, any arbitration clause contained therein may likewise be void. This may be true even where neither party objected to the arbitration clause per se.

Although the Patriot Court stated that generally, to be subject to arbitration, a party must be a signatory to the contract containing the arbitration clause, a signature is not a statutory requirement to enforce an arbitration clause. Louisiana’s arbitration statute, La. R.S.9:4201, requires only that the arbitration agreement be in writing. It does not require a signed contract. The jurisprudence is clear that the law does not require a signed agreement to arbitrate.  See Hurley v. Fox, holding that the defendant-architect’s motion to confirm the arbitration award could not be denied merely on the ground that the plaintiff-homeowner never signed the contract. See also Rainey v. Entergy Gulf States, Inc., in which the Louisiana Supreme Court held that a party who drafts a contract and presents it to another for signature cannot claim the contract is unenforceable because that party never signed the contract. Even where the parties contemplate that both parties will sign the contract to signify acceptance, a contract may nevertheless be valid without both signatures where the non-signing party has availed itself of the agreement or taken action evidencing its acceptance of it.*

However, the result hinges on the parties’ intent – as determined by the written agreement. For example, where the written contract expressly conditions validity on both signatures, a missing signature is likely fatal to the enforcement of any arbitration clause contained in the contract.  See Huckaba v. Ref-Chem, LP, in which the U.S. Fifth Circuit invalidated an arbitration provision in an employment contract where the employee signed it but the employer – who sought to enforce the arbitration clause – did not.

Also noteworthy, an arbitration clause in a contract signed by both parties may nonetheless be invalid where the court finds that fraud, duress, or other vice was involved in the formation of the contract such that one party did not truly consent to the contract terms. In the recent case Mapp, LLC v. Floor and Decor Outlets of America, Inc., the U.S. Fifth Circuit held that a contract was unenforceable because it was found to be adhesionary – it gave the owner, which had superior bargaining power, sole discretion to invoke arbitration.

In Carver Theater, LLC v. Melancon, another noteworthy case, an arbitration clause in a written contract signed by both parties was enforced by the Court and resulted in an arbitration award. However, it was later determined invalid – and the award was also invalidated –where the party that initially sought to enforce arbitration later changed its position and argued that the contract was invalid.  The Court invalidated the arbitration award under the Louisiana arbitration statute, finding that the award was procured using “undue means.” In seeking to compel arbitration, the party argued that the contract was valid and required arbitration. Once in arbitration, that same party argued that the contract was invalid. This misrepresentation to the Court satisfied the statute’s narrow grounds for invalidating an arbitration award.**

As a final consideration, non-signatories such as subcontractors or sureties may be compelled to arbitrate where their subcontract or bond incorporates by reference the contract containing the arbitration clause and where the language in that arbitration clause is sufficiently broad, for example – any controversy or claim arising out of or related to the contract. See The Jewish Federation of Greater New Orleans, et al. v. Fidelity & Deposit Company of Maryland, holding that the surety was bound by the arbitration clause in the construction contract because its bond incorporated it by reference, even on its counterclaim for declaratory relief based on a defense that the performance bond had lapsed.

* See Harp v. Succession of Bryan, 2019-0062 (La.App. 1 Cir. 9/3/20), 313 So.3d 284; La. Civil Code art. 1927.

** La. R.S.9:4210(A).

References:

PatriotConstruction & Industrial, LLC v. Buquet & LeBlanc, Inc., 2023-557 (La. App. 3 Cir. 4/24/24), 387So.3d 784.

Hurley v. Fox, 520 So.2d 467 (La. App. 4 Cir. 1988).

Rainey v. Entergy Gulf States, Inc., 2009-572 (La.3/16/10), 35 So.3d 215.

Huckaba v. Ref-Chem, LP, 892 F.3d 686 (5th Cir.2018).

Mapp, LLC v. Floor and Decor Outlets of America, Inc., 2026WL 2265969, 25-30536 (5th Cir. 2026).

Carver Theater, LLC v. Melancon, 2024-0468 (La. App.4 Cir. 5/5/25), 417 So.3d 676. The court determined that the FederalArbitration Act and its severability doctrine did not apply in this case. Theresults may have been different under the FAA.

The Jewish Federation of Greater New Orleans, etal.  v. Fidelity & Deposit Company of Maryland, 273 F.3d 1094,2001 WL 1085096 (5th Cir. 2001) (unpublished).

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

A Matter of Control: Vicarious Liability in Construction Projects

Under Louisiana’s comparative fault system, each party in a lawsuit generally is only liable for their own percentage of fault. However, in some instances, a party may be “vicariously” liable for the fault of another party. One example of vicarious liability is an employment relationship, where an employer can be liable for the fault of its employees. On the other hand, vicarious liability generally does not apply when the alleged “employee” is found to be an independent contractor. Whether a worker qualifies as an employee or an independent contractor often becomes an important issue in suits related to construction projects.

The test for determining whether a party is an employee or an independent contractor involves analysis of who has the right to control his or her work. In the construction context, courts distinguish between “operational control” (which suggests an employment relationship) and control as it relates to the results of the work (which suggests an independent contractor relationship). Two recent cases examine this issue and provide examples of how courts analyze the type of control necessary to establish vicarious liability in the construction projects.

In Stonetrust Com. Ins. Co. v. TBT Contracting, Inc. of LA, homeowners hired a general contractor to renovate their home. During the project, an electrical subcontractor was injured after falling through an attic space. It was alleged that the general contractor created a hazard by cutting a hole in the attic and concealing it. The plaintiff sued the general contractor and the homeowner. The court had to determine whether the homeowner could be liable for the subcontractor’s injuries, which would require a finding that the homeowner was vicariously liable for the general contractor’s fault.

The plaintiff argued that the homeowners were particularly involved in the project. It presented evidence to show the homeowners would give suggestions regarding the work to be performed and also directed alterations or additions to the work. The plaintiff argued that this demonstrated control over the general contractor’s work. However, the court disagreed. Despite the homeowners’ level of involvement, the court held that their control was limited to the results of the work, and was not “operational control.” The general contractor therefore was an independent contractor, and the homeowners were not vicariously liable for its acts.

In Baham v. Fisk Elec. Co., a city worker brought suit against a general contractor after suffering injuries from an electrical shock. The worker alleged that the general contractor was vicariously liable for the fault of its subcontractor. While evidence showed the subcontractor relied on the general contractor for the location of its work, the court found that this was not “operational control.” The court observed that general contractors are entitled to exercise supervisory control over its independent contractors to ensure compliance with the contract. It further found that suggestions or instructions given to an independent contractor do not equate to control over the methods or details of the work. Absent such “operational control” vicarious liability could not be imposed.

Though they may be limited to their facts, these cases show courts usually require a showing of more than suggestions or instructions regarding the work to establish the “operational control” necessary to trigger vicarious liability. Absent such a showing, independent contractors usually remain independent.

Case References:

Stonetrust Com. Ins. Co. v. TBT Contracting, Inc. of LA, 2022-0971 (La. App. 1 Cir. 4/14/23), 2023 WL 2947826

Baham v. Fisk Elec. Co., 2022-0551 (La. App. 4 Cir. 3/22/23), 2023 WL 2595253

Insight

Risky Business : "Foreseeable" Damages in Commercial Transactions

Intuitively, contracting parties in commercial transactions understand that legal consequences follow a breach of contract: If a party fails to deliver a product as promised, the breaching party can be liable for the cost to correct the breach; but what is that cost?

Say, for example, a business cancels an order to provide parts to a long-time customer because the relationship has gone sour. Legally, the liability for that breach of contract may extend beyond the cost of the order. A breaching party is liable for damages that are a direct consequence of the failure to perform and that were foreseeable at the time the contract was made, which may include lost profit. If the breach was intentional or malicious, the party's liability may extend even to direct damages that were not foreseeable.

The business that cancelled the order now faces a jury’s decision to identify the direct and foreseeable losses, a decision that, by its nature, is vague. However, the law imposes a limit on the jury’s prerogative to decide the damages. Even for a bad faith breach of contract, liability arises only for the direct, immediate consequences of the breach and there should be no liability for damages determined to be remote, indirect, or that have no necessary relation to the breach.

In a recent case, a jury found that a defendant boat engine manufacturer breached its contract with plaintiff boat manufacturer by cancelling a purchase order for engines, and further, that the engine manufacturer was in bad faith. The jury awarded $1.8 million in foreseeable lost revenues and $1.3 million in unforeseeable lost profits. The trial court threw out the “unforeseen” portion of the award because it was not a direct damage, and emphasized that a breaching party does not “become the insurer for all misfortunes that may arise from the breach.”

The boat manufacturer had argued that the cash flow expected from the sale of the boats rendered engine-less by the breach would have been invested in more personnel and capital to grow its northwest division. But, because of depleted cash flow from lost sales, that opportunity was lost. The court found, as a matter of law, that this loss was not a direct consequence of the breach, and thus, regardless of the bad faith, was not a recoverable contract damage. Simply, loss of cash flow in one part of the business that had a ripple effect in a separate division was too indirect to be a recoverable damage. See Marine Power Holding, LLC v. Malibu Boats, LLC, 2016 WL 7241560 (E.D. La. 12/15/2016).

By contrast, courts have found that loss of cash flow is recoverable where directly related to the damages suffered, such as where breach of a contract to deliver chickens to a chicken farmer caused the forced sale of the chicken farm. See Volentine v. Raeford Farms of La., 50-698 (La.App. 2 Cir. 8/15/16), 201 So.3d 325.

Failure to perform on a contract exposes a business to more than it may realize. Understanding this risk allows for smarter decisions before the breach.

Insight

You’ve Been Served – Now What? Understanding “Louisiana’s Pre-trial Procedure”

A deputy arrives at your home or office and announces that you have been served. You quickly realize you have been named as a defendant in a lawsuit. Now what?Whether the suit involves a breach of contract, an automobile accident, or the one and a million other circumstances that can lead to a suit being filed, the process is essentially the same in Louisiana state courts. This blog provides a general roadmap of Louisiana’s “pre-trial” procedure, which applies in most situations. Different procedures are involved with workers’ compensation claims, administrative proceedings, medical malpractice claims, and other areas.Petition/Answer - When a person or company believes they have been damaged by fault, breach, or neglect, Louisiana law provides that the person allegedly wronged, the plaintiff, may file a Petition for Damages. Louisiana does not have a “loser pays” system. For this reason, there is little disincentive to a plaintiff who wants to sue. Once the Petition is filed with the Clerk of Court, the Sheriff serves the defendant with a certified copy of the Petition and the “Citation.”A defendant has fifteen days to file an Answer or to secure an extension from either the plaintiff attorney or the Judge, by filing a Motion for Extension of Time to File Responsive Pleadings. A failure to respond to a suit or obtain an extension within 15 days of service may result in a default judgment.Trial by Judge or Jury -The parties advise if they desire a judge or jury trial in the initial filings. There is no right to a jury in cases which do not have a possible value of more than $50,000. If a plaintiff “stipulates” that case value is at or below $50,000, the defendant has no right to demand a jury trial under Louisiana Code of Civil Procedure article 1732.Exceptions - Defendants have the right to raise “exceptions” to the suit. Common exceptions include a claim that the suit is vague; is filed in the wrong venue (i.e., the wrong location); or is untimely, and therefore “prescribed.” Defendants can use the exception process to challenge the plaintiff’s legal ability to recover. Many exceptions are waived if they are not filed before or with the Answer.Discovery

  • Written - After the Answer is filed, the discovery process typically begins. Discovery is an information-gathering process done through different methods. The parties to a lawsuit may issue written Interrogatories, Requests for Admission, and Requests for Production of Documents.
  • Depositions - Depositions are a key component of discovery. A deposition allows the attorneys (or the parties themselves, if unrepresented) to ask questions of witnesses before a court reporter. The testimony is taken under oath and can be used later for certain purposes. For example, if the witness is not available to testify at trial, the deposition testimony can often be introduced in lieu of live testimony. Also, if a witness changes his testimony at trial, the deposition can be used to attack the testimony and credibility of the witness.

Case Deadlines - Typically, the court will establish a scheduling order to establish key dates such as deadlines to identify witnesses, exhibits, and any experts who may testify on behalf of the parties. The court often sets a deadline to file “dispositive” motions, such as motions for summary judgment where the plaintiff or the defendant tries to have the case determined before the trial.Alternative Dispute Resolution - Frequently, the parties agree to attempt to mediate the case with the assistance of a mediator. This is a voluntary process. In some cases, the parties will be bound by an agreement to arbitrate which will be conducted outside of the normal court process.There is no law or statute which sets the time frame for the “pre-trial” process. Depending upon the complexity of the suit, the pre-trial phase of a suit may take months, and often years.