When You Can’t Sue – Limits on Contractor Liability

Published on: January 25, 2017

Louisiana law protects building contractors from liability for past projects that otherwise could extend for an indefinite period of time. La. R.S. 9:2772 prohibits any lawsuit against a contractor for damages arising from a construction project five years after: (1) the date project acceptance was filed into the public records; or, if no acceptance was filed, (2) the date of occupancy. This five-year period is referred to as the "peremptive" period.

This law is broad enough to bar untimely claims of breach of contract and negligence, as well as failure to warn of dangerous conditions. It also covers all conceivable building activities: design, construction, consultation, planning, evaluation, construction administration, and land surveying. It applies both to residential and commercial construction. It also covers claims of property damage, personal injury, and wrongful death brought by any person. The only noted exception is where a contractor’s fraud caused the damages.

The law is meant to establish a specific date to cut off the contractor’s liability. Under the law, nothing can interfere with the running of a peremptive period. After it expires, the claim no longer exists.

Construction litigation in this area often focuses on commencement of the peremptive period. For instance, in Celebration Church, Inc. v. Church Mutual Insurance Company, 16-245 (La.App. 5 Cir. 12/14/16), the owner of a shopping center sued its property insurer for roof damage related to Hurricane Isaac. The insurer prevailed in defending the claim based on defective roof repairs made following Hurricane Katrina. The owner then filed suit against the roofer who made the repairs after Hurricane Katrina. To avoid the peremptive defense, the owner argued that peremption did not begin to run until substantial completion of the entire shopping center. The court rejected this argument and held that the law is specific in defining the date of commencement of the peremptive period. It began to run when the tenants first occupied the space. By the time suit was filed, the owner’s claim no longer existed.

Because construction defects may not surface for years, a claim may be barred before the owner even discovers the problem.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

When You Can’t Sue – Limits on Contractor Liability

Louisiana law protects building contractors from liability for past projects that otherwise could extend for an indefinite period of time. La. R.S. 9:2772 prohibits any lawsuit against a contractor for damages arising from a construction project five years after: (1) the date project acceptance was filed into the public records; or, if no acceptance was filed, (2) the date of occupancy. This five-year period is referred to as the "peremptive" period.

This law is broad enough to bar untimely claims of breach of contract and negligence, as well as failure to warn of dangerous conditions. It also covers all conceivable building activities: design, construction, consultation, planning, evaluation, construction administration, and land surveying. It applies both to residential and commercial construction. It also covers claims of property damage, personal injury, and wrongful death brought by any person. The only noted exception is where a contractor’s fraud caused the damages.

The law is meant to establish a specific date to cut off the contractor’s liability. Under the law, nothing can interfere with the running of a peremptive period. After it expires, the claim no longer exists.

Construction litigation in this area often focuses on commencement of the peremptive period. For instance, in Celebration Church, Inc. v. Church Mutual Insurance Company, 16-245 (La.App. 5 Cir. 12/14/16), the owner of a shopping center sued its property insurer for roof damage related to Hurricane Isaac. The insurer prevailed in defending the claim based on defective roof repairs made following Hurricane Katrina. The owner then filed suit against the roofer who made the repairs after Hurricane Katrina. To avoid the peremptive defense, the owner argued that peremption did not begin to run until substantial completion of the entire shopping center. The court rejected this argument and held that the law is specific in defining the date of commencement of the peremptive period. It began to run when the tenants first occupied the space. By the time suit was filed, the owner’s claim no longer existed.

Because construction defects may not surface for years, a claim may be barred before the owner even discovers the problem.

Insight

Making the Case for Arbitration of Commercial & Construction Disputes

Clients frequently ask their attorneys whether they should arbitrate their commercial and construction disputes instead of litigating in the court system. This question arises either when drafting the contract or, if the contract contains an arbitration clause, once a claim occurs. Claims that require analysis of complex contracts, government regulations, and technical issues, such as those that arise in the construction, environmental, and energy industries, are well-suited to arbitration.

Parties typically want the quickest and least expensive means to a fair result. This is true even for highly sophisticated businesses where the amount in dispute is high. Arbitration gives parties a high level of control in the dispute resolution process. It is specifically designed to provide an alternative to the onerous and expensive discovery and trial procedures required in litigation. Parties can tailor the discovery and schedule to the needs of the case, which drastically reduces the overall time and cost of reaching resolution.

Arbitration also allows parties to select an arbitrator with specialized knowledge necessary to decide the case, which is especially beneficial in complex cases. Because parties agree to arbitration in their contract, they have control over the process in a way that is not available in litigation. For example, the parties may designate the administrative body and applicable rules, require a three-arbitrator panel for a complex case, name a particular arbitrator, require confidentiality, or dictate the timeframe for the hearing.

The following four factors are key considerations in assessing arbitration:

Expertise of decision-maker – One of the most important benefits of arbitration is the parties’ ability to select the arbitrator. This affords parties an opportunity to designate a decision-maker with specific qualifications and expertise needed to understand the contracts, legal issues, engineering and technical facts, and expert evidence to be presented. The parties can also select someone with strong management skills to handle complex matters or difficult decisions. The benefit is two-fold: Fewer resources are needed to educate the decision-maker in the critical industry background information, and the risk of an unreasonable ruling is reduced.

Timeframe for resolution – The median time to resolution in commercial arbitrations is less than one year, whereas the time to trial in federal court is two to three years.* Because appeal rights in arbitration are limited, the award typically terminates the dispute and the expense. However, after a trial, the case could linger through the appeal process for several more years, thus increasing the expense.

In addition to direct cost saving, decreasing the resolution time creates an indirect cost benefit to industry. Because “time is money,” shaving years off the process results in significant savings that likely can be better used advancing the business than litigating a case. Businesses lose billions of dollars every year because of the inherent delays in the litigation process.^ These losses stem from uncertainty in the outcome, capital set aside as reserves for potential losses, open claims reported to insurers, investors, potential clients and auditors, and loss of employee hours and administrative costs expended in litigation. Arbitration offers an alternative to mitigate and control these costs.

Expense – Arbitration typically costs more upfront than litigation. The parties must pay the administrative costs and arbitrator fees, which vary depending on the time and complexity involved, but generally range from $20,000 for a $100,000 claim to $60,000 for a $1 million claim. The costs are shared among the parties, which decreases the per-party cost in multiparty claims.

However, parties can control the cost of arbitration. Discovery, depositions, and document production in complex cases can come with staggering costs. In arbitration, the rules governing discovery and evidence are less formal. Additionally, discovery is more limited, which encourages a streamlined process and reduces costs and time significantly.

Risks – An often-cited risk of arbitration is the lack of appeal right. An arbitration award can only be vacated on limited grounds of fraud, corruption, misconduct, or where an arbitrator exceeds their power.~ However, if the initial decision-maker has expertise in the industry and law involved, the expectation is that the decision will be a well-reasoned one that the parties can accept.

In contrast, a major risk of litigating a complex commercial dispute is the fact-finder’s lack of understanding of the issues, the escalating potential for nuclear verdicts, and the appellate court’s limited power to correct factual findings.

In sum, arbitration is a good choice for dispute resolution where parties want to control the risk of an unreasonable outcome, reduce the time and expense of the process, and select a decision-maker with special expertise in their industry.

About the author: Mary Anne Wolf is an engineer and attorney. She is on the panel of commercial and construction arbitrators for the American Arbitration Association. Her goal as an arbitrator is to assist parties in managing their case for efficient resolution, give a high level of attention to each party’s position, and achieve a fair result.

References:

* AAA, Measuring the Costs of Delays in Dispute Resolution [online]; Micronomics, (March 2017), Efficiency and Economic Benefits of Dispute Resolution through Arbitration Compared with U.S. District Court Proceedings.

^ Efficiency and Economic Benefits, pp. 4-5, 16-23.

~ La. R.S. 9:4210 (LA Binding Arbitration Act); 9 USCA §10 (FAA).

Insight

Pass-Through Claims and Prescription

In Couvillion Group, LLC v. Plaquemine Parish Government, the Louisiana Court of Appeals for the Fourth Circuit addressed whether the general contractor could recover “pass-through claims” against the owner where those claims would be time-barred if brought directly by the subcontractors. “Pass-through claims” have been described as damage claims that subcontractors “pass through” to the contractor to prosecute an action against the project owner to recover those damages.

In Couvillion, the contractor sued the Parish for delay damages. The trial court awarded $2,782,724 in delay damages, $300,000 of which was for delays incurred by two of the subcontractors.

On appeal, the Parish argued that the contractor could not recover the pass-through claims because any claims for delay that the subcontractors had against the contractor were prescribed (time-barred). The subcontractors sent demand letters after substantial completion in 2013 but did not file suit against the contractor. Under Louisiana law, contract claims are subject to a 10-year prescriptive period. The Parish asserted that by the time trial occurred in 2024, the subcontractor claims had prescribed.

The Fourth Circuit recognized that subcontractors often pass their claims through the contractor to prosecute against the owner to recover those damages. The contractor included those claims in the lawsuit filed against the owner in 2015. When several parties share a cause of action, suit by one party interrupts prescription as to all parties. As such, the court held that prescription was interrupted, and the contractor could recover the pass-through claims against the owner.

This case highlights the importance of identifying and properly preserving pass-through claims early in litigation.

References:

Couvillion Grp., LLC v. Plaquemines Par. Gov't, 2025-0356 (La. App. 4 Cir. 1/7/26), 430 So. 3d 1175, writ denied, 2026-00217 (La. 5/12/26), 430 So. 3d 1090.

‍