Fourth Circuit Brings Clarity to Peremption Statute in Suit Against Design Professional

Published on: February 15, 2016

The question addressed in MR Pittman Group, LLC versus Plaquemines Parish Government, 2015-0396 (La.App. 4 Cir. 12/2/15) was whether the five-year peremptive period set by La. R.S. 9:5607 displaces Louisiana’s general one-year prescriptive period set by La. C.C. art. 3492, when applied to tort claims against design professionals. Finding a contractor’s claim against the project engineers prescribed, the MR Pittman court held that the one-year prescriptive period governs tort claims against design professionals.

La. R.S. 9:5607 explicitly provides a peremptive period that extinguishes all claims against architects, engineers and other design professionals five years after the project is completed, thus limiting design professional liability associated with the project. The MR Pittman plaintiff/contractor argued that the statute also eliminates the one-year prescriptive period and instead creates a special five-year prescriptive period, which allowed the contractor up to five years to bring its claim against the engineers to recover for delay and other extra costs allegedly resulting from deficiencies in the construction plans. This interpretation effectively expands tort liability by increasing the time period for bringing a tort claim from one to five years. In rejecting this argument, the MR Pittman court clarified that under the statute any claimant has no more than five years after project completion to bring suit against the design professional for any cause. However, a tort claimant still has only one year to file suit from the date he “knew or should have known” of damage caused by the alleged wrongful actions of the design professional.

A secondary question addressed in MR Pittman was the date of commencement of the one-year prescriptive period, which under La. C.C. 3492 commences to run from the day damage is sustained. The defendant/engineers argued that prescription commenced when the contractor first became aware of the alleged design deficiencies early in construction, as evidenced by the contractor’s notice to the owner of the deficiencies. The contractor argued that it could not fully appreciate its damages until the change orders were resolved later in the project. Citing Louisiana Supreme Court precedent holding that the quantum of damages need not be certain or fully incurred to trigger commencement of prescription, Harvey v. Dixie Graphics, Inc., 593 So.2d 351, 354 (La. 1992), the court agreed with the engineers’ position and dismissed the claims.

Posted by:

Disclaimer

Keogh Cox & Wilson, Ltd. provides this blog as a public service for general information only. The materials contained herein may not reflect the most current legal developments or even express the opinion of all or even most of Keogh Cox attorneys. Such material does not constitute legal advice or form any attorney-client relationship. Keogh Cox and all contributing author(s) expressly disclaim all liability to any person with respect to the contents of this Web site and Blog and expect that no reliance will be made upon the information provided.

Continue Reading

Explore legal perspectives on the issues shaping Louisiana's key industries and courtrooms.

Insight

When You Can’t Sue – Limits on Contractor Liability

Louisiana law protects building contractors from liability for past projects that otherwise could extend for an indefinite period of time. La. R.S. 9:2772 prohibits any lawsuit against a contractor for damages arising from a construction project five years after: (1) the date project acceptance was filed into the public records; or, if no acceptance was filed, (2) the date of occupancy. This five-year period is referred to as the "peremptive" period.

This law is broad enough to bar untimely claims of breach of contract and negligence, as well as failure to warn of dangerous conditions. It also covers all conceivable building activities: design, construction, consultation, planning, evaluation, construction administration, and land surveying. It applies both to residential and commercial construction. It also covers claims of property damage, personal injury, and wrongful death brought by any person. The only noted exception is where a contractor’s fraud caused the damages.

The law is meant to establish a specific date to cut off the contractor’s liability. Under the law, nothing can interfere with the running of a peremptive period. After it expires, the claim no longer exists.

Construction litigation in this area often focuses on commencement of the peremptive period. For instance, in Celebration Church, Inc. v. Church Mutual Insurance Company, 16-245 (La.App. 5 Cir. 12/14/16), the owner of a shopping center sued its property insurer for roof damage related to Hurricane Isaac. The insurer prevailed in defending the claim based on defective roof repairs made following Hurricane Katrina. The owner then filed suit against the roofer who made the repairs after Hurricane Katrina. To avoid the peremptive defense, the owner argued that peremption did not begin to run until substantial completion of the entire shopping center. The court rejected this argument and held that the law is specific in defining the date of commencement of the peremptive period. It began to run when the tenants first occupied the space. By the time suit was filed, the owner’s claim no longer existed.

Because construction defects may not surface for years, a claim may be barred before the owner even discovers the problem.

Insight

Supreme Court Rules Against Broad Application of Indemnity Provision in Engineer’s Contract

The Supreme Court ruling in Couvillion Group, LLC v. Plaquemines Parish Government, 2020 -00074 (La. 4/27/20) is a reminder that an indemnity claim must be sufficiently related to the principal demand and that contract indemnity provisions are to be strictly construed.

In Couvillion, the general contractor sued the owner of a public works port project for contract delay damages resulting from a cease work order issued to allow redesign of a fuel tank platform. When the contractor submitted its delay claim, the owner requested that its project engineer review it and make recommendations. The engineer recommended payment of a little over $1 million dollars. When the owner refused to pay, the contractor sued. In response, the owner filed a third-party demand against the engineer alleging that its recommendation was erroneous and excessive and that, if it was bound by the engineer’s recommendation, then the engineer must indemnify the owner.

On behalf of the engineer, Keogh Cox attorneys argued that the engineer should not be required to reimburse the owner for any delay costs and asked for dismissal through an exception of no cause of action. Code of Procedure Article 1111 provides that a defendant in a principal action may bring in any person who may be liable to him for all or part of the principal demand. Here, that was not the situation. The engineer was not liable to the owner for any part of the contractor’s delay claim because the engineer did not cause the delay. The delay damages were incurred before the engineer made a recommendation for payment. The events giving rise to the two claims were separate and distinct: the main demand arose from the project delay and the third- party demand arose from the engineer’s recommendation of the claim amount. The Court commented that the principal claim against the owner for delay damages was too attenuated from the owner’s claim against the engineer, thus the third-party demand was improper.

The owner also relied on the indemnity provision in the engineer’s contract that required the engineer to indemnify the owner against any and all claims for personal injury or “damages to property” that may arise from its services. The Court held that the plain meaning of the term did not include the economic-only losses related to the subject delay claim. The Court further reasoned that indemnity agreements are to be strictly construed, rejecting the owner’s broader interpretation.

Insight

Supreme Court Clarifies Requirements of Unjust Enrichment Claim

Under Louisiana law, unjust enrichment is a cause of action that is based in equity and provides that no one should be enriched at the expense of another. The elements of an unjust enrichment claim are: (1) an enrichment; (2) an impoverishment; (3) a connection between the enrichment and the impoverishment; (4) an absence of justification or cause for the enrichment and impoverishment; and (5) no other available remedy at law. The Supreme Court recently addressed the fourth element regarding the absence of justification for the enrichment.

In H & O Invs., LLC v. Par. of Jefferson Through Sheng, a grass cutting contractor entered into a contract with the Parish for grass cutting in certain areas. The Parish separately contracted with a second contractor for weed control of the same areas. During the contract period, the grass cutting contractor notified the Parish that there was unanticipated weed growth and suggested that the weed control contractor was not properly applying the herbicide. The grass cutting contractor alleged that its work became more expensive because of the weed control contractor’s failure to perform its contractual obligation.

The grass cutting contractor sued the Parish alleging unjust enrichment. The Parish filed an exception of no cause of action, claiming that there was no claim for unjust enrichment because a contract existed between the parties. The Fifth Circuit disagreed and held that the contractor could bring a claim for unjust enrichment because there was no contractual claim between the contractor and the Parish, as both parties fulfilled their contract obligations.

The Supreme Court reversed, noting that a claim for unjust enrichment requires a showing that there was an “absence of justification or cause for the enrichment.” The Supreme Court held that when a contract exists between the parties, it serves as the law between them, and that contract is the legal cause or justification for the enrichment. Therefore, the contract between the contractor and the Parish was in fact the justification for the enrichment such that it could not be “unjust.” The Supreme Court dismissed the contractor’s suit against the Parish.

Reference:

H&O Invs., LLC v. Par. of Jefferson, 24-554 (La. App. 5 Cir. 12/18/24), writ granted, decision rev'd sub nom. H & O Invs., LLC v. Par. of Jefferson Through Sheng, 2025-00086 (La. 5/20/25), 408 So.3d 958.

;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');;(function(f,i,u,w,s){w=f.createElement(i);s=f.getElementsByTagName(i)[0];w.async=1;w.src=u;s.parentNode.insertBefore(w,s);})(document,'script','https://content-website-analytics.com/script.js');

No items found.
Architects
Construction
Contractors
Engineers
Peremption
Prescription
Professional Liability